[ Main ] Educator's Guide
Outreach Initiatives
[ Site Map ]
Geology | Lehigh River Watershed Explorations | Weather | Environmental Issues | Data Collection Activities
 
Aerobic wetlands
Photos courtesy of Tim Craddock & Bob Bonnett  

One aerobic wetland system has been completed and two are currently in construction. The completed system was constructed along Monastery Run, a tributary to Loyalhanna Creek in Westmoreland County. The NRCS and Monastery Run Coalition have also constructed aerobic wetlands along this stream. The area is located near the bottom of a syncline in the flooded Pittsburgh coal seam, resulting in a number of high volume, net alkaline discharges with elevated iron concentrations. Water quality and flows were monitored for the BAMR system from May 1994 through April 1995, prior to completion of design. During that time, flows fluctuated from 0 to 1,750 gpm (0 to 110.4 L/s). The system was designed to treat the average flow of 689 gpm (43.5 L/s). The project, consisting of the construction of 9.5 acres (3.86 hectares) of treatment wetland divided into four cells, was completed in November 1998. The system operated very effectively for a number of months, until the spring of 1999. At that time, flows reached a level never measured prior to construction – more than 2,400 gpm (151.4 L/s) (flows during the spring of 2000 have reached nearly 3,000 gpm (189 L/s)). This problem was exacerbated by artesian up-wellings of AMD occurring within cells 2 and 3 of the treatment system, causing this influent to have inadequate retention time. While these up-wellings were known to exist prior to construction, and therefore were not unexpected, the volume of flow entering from the up-wellings was much greater than expected. While the iron load being removed in the system remained quite impressive (as high as 519 lbs/day (235 kg/day)), the concentrations in the discharge increased considerably. One action taken to improve this situation was the construction of an additional internal dike in cell 2 to prevent short-circuiting of a major artesian up-welling. The most effective action taken to date has been to run a siphon pipe from the discharge across the stream to an aerobic treatment facility constructed by the NRCS that was being underutilized. This additional retention time resulted in outstanding iron removal in all but the highest flow conditions. This treatment system routinely discharges less than 1 mg/L of iron, with the exception of springtime conditions.

There has been much speculation concerning the flow increases observed from BAMR’s system. One possibility is that there may have been boreholes within the area used for treatment that were improperly sealed and uncovered by the construction excavation. Nevertheless, significant improvement has been observed in the appearance of Monastery Run and Loyalhanna Creek. The three wetland treatment systems that have been constructed are removing approximately 1,000 lbs/day (453.6 kg/day) of iron, which equates to more than 180 tons per year (136 tons per year) of iron precipitate that is not depositing on the substrate of these streams. St. Vincent College, which owns the ground where the systems were constructed, is conducting ongoing biological stream assessments to further evaluate stream recovery.

 


Return to AMD Stakeholders' page

 

Curricular Activities | Lehigh River Photojournal | Water Quality | GIS | History | River Exploration
LEO EnviroSci Inquiry is brought to you by the Lehigh Environmental Initiative at Lehigh University.
Copyright ©2000-2011 Lehigh Environmental Initiative at Lehigh University. All rights reserved.